|
|
Formal Safety Assessments (FSA) |
Bookshop
Acronyms
/ Definitions
|
The International Maritime Organization (IMO) identifies the following five stages as being part of an FSA.
As with everything else to do with safety cases, the nature and content of an FSA will vary according to local conditions and requirements. The management of safety is both non-prescriptive and performance-based. The information provided here provides a framework for the development of an actual FSA that meets the specific needs of a facility or project. Guidance is also provided in ISO 31010: Risk Management - Risk Assessment Techniques.
An FSA is a demonstration that, so far as is reasonably practicable, the risks
to personnel have been minimized. It should:
Elements of an FSAAn FSA will be structured to meet the needs of the facility being analyzed. An example is provided in Table 1.
Table 1
Elements of a Formal Safety Assessment
A summary discussion of each of the above topics is provided below. Links to more detailed pages are provided where appropriate. 1. Project HSE PlanA safety case is concerned primarily with the safety of the facility once it has been built and is in operation. However, the project itself has its own set of hazards, particularly during the fabrication and construction stages (which may have their own safety case). Therefore a Health, Safety and Environmental (HSE) plan for the project itself should be prepared and incorporated into the FSA.HealthThe Project HSE plan will cover health issues such as the treatment of minor injuries and precautions to be taken when traveling overseas. SafetyThe plan will also show how safety on the project is to be managed. In the front end phases of the project the focus will be on issues such as safe driving, the development of safety moments with which to start meetings and a schedule for project safety meetings. As already noted, safety during the construction phase of the project is a major concern and will often have its own safety case. EnvironmentGeneral environmental issues, such as not disposing of items overboard, will be included in the Project HSE Plan. The environmental plans and impact statements to do with the facility itself once it is in operation are usually prepared by specialist consulting groups or consultants. 2. Safety in Design PhilosophyThe Safety in Design (SID) Philosophy has three primary purposes. First, it should how the different elements of the FSA (Table 1), and of the safety case in general, link to one another.
Second, it should show how overall risk is assessed and controlled. 3. Assumptions RegisterThe project plan should include an Assumptions Register. A convenient place to locate this register is in the Safety in Design Philosophy. This register will contain a list of the assumptions used to develop the Formal Safety Assessment. (An alternative approach would be to put the assumptions for each topic into the deliverable for that topic. The justification for the assumptions made should be provided. Generally, the justification will come from one of three sources.
Some of the assumption topics are listed below. Deck TypeThe results of blast and gas dispersion analyses vary significantly depending on whether the deck is plate or grate. Therefore the assumptions made as to the type of deck to be used in various parts of the platform need to be made explicit. Numbers of Personnel and their LocationsThe Assumptions Register should specify how many people are on the platform, and where they are most likely to be located. An estimate as to peak manning loads, say during drilling, should also be provided. Leak SizeThe assumptions made as to the size of leaks from flanges, fittings, piping, instruments and vessels need to be documented. Leak FrequenciesAn estimate as to the frequency with which leaks can occur is required. The frequency value will generally vary inversely with hole size. Transportation LogisticsAn important part of the safety case is estimating the frequency and consequence of accidents involving helicopters, work boats and other forms of transportation. The types of transportation to be used, and the number of journeys made has to be estimated. Assumptions to do with ship collisions (including pleasure boats that may be present) should be written down. Factors to consider include the speeds at which collisions may occur, and whether collisions occur while boats are maneuvering or drifting. Lifting OperationsAssumptions to do with lifting operations need to be spelled out as a basis for the Material Handling study. Issues to be itemized include:
Guidance should be provided as to the percentage of drops that occur over the deck, over the side (into the sea), and into a work boat. Rescue and Recovery OperationsAssumptions as to the effectiveness of emergency response and rescue operations need to be spelled out. MetOcean DataThe Assumptions Register should contain meteorological information, covering both normal and extreme weather conditions. The information should include:
Structural Failure TimeAssumptions have to be made regarding the time it takes for steel structures to fail when they are exposed to fire. An example is provided in Table 2.
Table 2
4. Hazards RegisterDuring the course of a project the facility design will be subject to a series of hazards analyses of various types. It is important that all identified hazards be captured in a single data base so that they can be managed, controlled and not overlooked. The hazards register (sometimes called the risk register) is used to store information about all identified hazards. Although most of the items in the register will come from hazards analyses, some of the hazard information may come from other sources, such as incident investigations or lessons learned from other facilities. Table 3 is an example of a Hazards Register. It will be managed and updated by a single person — often the same person as scribes the hazards analysis meetings.
Table 3
The rows to do with hazard identification are discussed below. Finding Number and DateEach identified risk item is given its own number — often corresponding to a finding from a hazards analysis or from a Management of Change review. HazardThe identified hazard is described in this row. A perennial complaint to do with hazards analysis reports is that they are too cryptic, and that insufficient background material is provided. Therefore It is important to provide as much detail at this point — people who read and use the register months or even years later will not have any knowledge of the discussion that led up to the creation of the finding. SourceThe register should contain information as to how and where the hazard was identified. Typically this will be a hazards analysis, but the information may come from other sources such as incident investigations or employee observations. Consequence(s) / Likelihood / RiskThe hazards analysis team spells out the hazard, consequence and likelihood for each finding. A perennial complaint to do with hazards analysis reports is that they are too cryptic, and that insufficient background material is provided. Therefore It is important to provide as much detail at this point — people who read and use the risk register months or even years later will not have any knowledge of the discussion that led up to the creation of the finding. Follow-UpThe follow-up section of the risk register describes how the identified hazard was handled, and when the associated recommendation was completed. On a large project it is necessary to have one person who is assigned the task of making sure that all findings are closed out properly before the new facility is started up. In addition to managing the register itself, the person in charge of follow-up generally is assigned the broader responsibility of filing all of the hazards analysis reports. Questions that have to be answered in this context include:
5. Hazard IdentificationThe identification of hazards is fundamental to any risk management program. This topic is discussed extensively elsewhere on this web site. For an FSA the following methods are particularly pertinent: 6. Layout Hazard ReviewGuidance to do with layout, and its relationship to Inherent Safety, is provided by the United Kingdom Offshore Operators Association. Some of the layout items to consider include the following:
7. Major Accident Events / Safety Critical ElementsMajor Accident EventsA major accident event (MAE) is one that has a high consequence. Large fires, explosions and toxic gas releases fall into this category. An important part of the FSA is to identify these MAEs and to ensure that they are properly controlled. Safety Critical ElementsThe term “safety critical element (SCE)” is sometimes used during the preparation of a safety case. The term refers to a part of an installation or facility whose failure could contribute substantially to a major accident, or whose purpose is to prevent, or limit the effect of, such an accident. DocumentationGiven that SCEs are so important to the safety of offshore facilities, it is important that everything to do with them is properly documented, and that the documentation is kept up to date. Depending on what the SCE is, documentation will generally include:
8. Fire and Explosion AnalysisThis topic is discussed in another web page at this site. 9. Gas and Smoke Dispersion AnalysisGas DispersionThis topic is discussed in another web page at this site. Smoke DispersionAn analysis of the smoke plume that can come from a fire is important (most of the deaths on the Piper Alpha platform were of men in the quarters who were overcome by smoke). Stability ClassIn general, the higher the wind speed the more quickly the plume disperses because the air is more turbulent. Atmospheric stability is divided into the six classes (Pasquill 1961) shown in Table 4.
Table 4
10. Non-Hydrocarbon AnalysisThis topic is discussed in another web page at this site.11. Emergency Evacuation, Escape and Rescue AnalysisThis topic is discussed in another web page at this site. 12. Emergency Systems Survivability Analysis13. Temporary Refuge14. Environmental Analysis15. Quantitative Risk Assessment (QRA)16. As Low as Reasonably Practicable Risk ¾ ALARPGiven that risk is basically subjective it is not possible to dispassionately define what level of risk is acceptable and what is not. After all, if a facility operates for long enough, it is certain ¾ statistically speaking ¾ that it will experience an accident. Yet, given that real-world targets are needed for implementing safety cases, a value for “acceptable safety” is needed. The ALARP page discusses this troublesome topic. 17. Noise AnalysisThis topic is discussed in another web page at this site. 18. Material HandlingThis topic is discussed in another web page at this site. 19. Health Risk AssessmentThis topic is discussed in another web page at this site. 20. Human Factors EngineeringHuman reliability analysis would normally be analyzed as part of the facility's Reliability, Availability and Maintainability (RAM) program. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Copyright © Sutton Technical Books 2007-2012. All rights reserved 6340 N. Eldridge Parkway, Ste-I #206 |