| Management of Change in the Process Industries |
|
Hence, the proper management of change is the foundation of all safety and accident prevention programs; an effective Management of Change (MOC) creates an atmosphere of "no surprises". Likewise, the day-to-day lives of everyone associated with that operation will flow more smoothly and productively when operations are stable. It is when there are upsets and unexpected problems that managers are subject to out-of-hours telephone calls from the plant, complaints from unhappy customers and unsolicited offers of help from corporate headquarters. Because of its central role in assuring safety, Management of Change is a critical component of all Process Safety Management (PSM) programs. The Meaning of the Word "Change"It is imperative to clearly define the word "change" in the context of a Management of Change program. OSHA considers a change that is not a "replacement in kind" as one that requires an MOC review. However the term "replacement in kind" needs further definition. After all, as discussed below, all changes are "not in kind" if examined closely enough. Some thoughts on the types of change that take place in a process facility are provided below. Initiated ChangeAn initiated change occurs when someone, usually a manager or an engineer, decides that he or she would like to modify the operation so that conditions move outside the current safe operating range. The following are examples of initiated change:
Reactive ChangeA reactive change is one that occurs spontaneously; unlike initiated change a reactive change is not created by a person's conscious decision. Corrosion is a common example of a reactive change; a vessel or a pipe may be gradually losing wall thickness without anyone knowing about it until an unplanned incident, such as a leak from a pipe, occurs.Organizational and personnel changes are often reactive. For example, management may decide to eliminate a night-shift position in the lab, not realizing that they system has now "changed" and that safety-critical analyses may not be available to the operations personnel. Reactive changes cannot be effectively controlled by the Management of Change program because they occur by themselves, not because someone wishes for them to occur. Therefore reactive changes have to be through other elements of the facility's Process Safety Management (PSM) program. These elements include Equipment and Instrument Integrity, Process Hazards Analysis and Incident Investigation. Overt ChangeReactive Changes can be either overt or covert. An overt change is one that is known about, and whose consequences can be mitigated before an accident actually takes place. For example, if an operator notes that a key variable such as a reactor temperature or a tank level is getting out of control, he or she is witnessing an overt reactive change. If allowed to continue, an accident may occur, so some sort of action must be taken.
Covert ChangeA covert change is not known about before it "announces" itself - often quite suddenly. For example, if no one knows that a particular pressure vessel is corroding, then the first indication of a problem will be when the vessel starts to leak. It is not generally possible to install safeguards to identify covert, reactive changes because those changes are inherently unpredictable. In-Kind / Not-In-Kind ChangeThe phrase "not-in-kind" change is used extensively in Management of Change literature, and has already been referred in the discussion to do with the OSHA standard. If an equipment item is to be replaced with one that is functionally identical, i.e., if the new item is built to the same specification as the old one, then the change is "in-kind". Otherwise it is "not-in-kind", and the MOC process has to be followed before the change can be implemented.The In-Kind/Not-In-Kind decision is critically important. The most challenging aspect of managing change is identifying that the proposed modification is in fact a change. An incorrect assumption that a proposed change is not-in-kind could lead to the occurrence of a serious incident. (The opposite scenario is less of a concern. If the change is incorrectly determined to be not-in-kind, but later turns out to be in-kind, then the only loss is that some time has been wasted on unnecessary evaluation.) Because of the criticality of this decision, the supervisors and lead operators need to be thoroughly trained on deciding whether a change should be in‑kind/not-in-kind, particularly since the choice of in-kind change offers a tempting way of by-passing the whole Management of Change process. Unfortunately, the distinction between in-kind and not-in-kind changes is not as simple as it might appear. In particular, there are two difficulties that must be considered in the context of Management of Change, the first of which is to do with circularity of meaning of the following type:
The second difficulty to do with the In-Kind/Not-In-Kind decision, noted above, is that all changes are, when analyzed deeply enough, not-in-kind. Even if an item of equipment is being replaced with a supposedly identical spare, there will always be differences between the replacement and original items. For example, the new item will have been made by different people, at a different time, possibly with different machinery. It may have been stored for a different length of time, and may be installed by different people, who have different levels of training and experience from those who made the first installation. When evaluated rigorously in this manner, all changes are not-In-kind. Generally, differences such as those just described will not be significant, but small changes can cause large accidents. On one facility, for example, a very serious accident resulted when a supposedly in-kind replacement gasket was inserted into a filter housing as part of a routine operation. The new gasket leaked, and a major fire ensued resulting in extensive equipment damage and many weeks of lost production (fortunately no one was injured). After the event it was determined that the new gasket was not in fact identical to the old one, even though all parties concerned had thought that it was. (A further significance of this incident was that the uncontrolled change occurred in the facility's warehouse - an area that would not normally be considered when developing Management of Change programs.) Based on the above discussion, a replacement equipment item can be judged to be in-kind if it meets the following criteria:
The Change ProcessAn eight-step process for implementing a Management of Change (MOC) process is illustrated in Figure 1 below. This structure attempts to address all the issues that need to be covered when evaluating and recommending change. Even if a different system is being used, each of the topics described in this eight-step approach should be covered by whatever Management of Change system is being used.Figure 1 Section A - Initiator RequestThe change process starts when someone identifies a problem that needs to be corrected, or believes that there is a better way of operating the process. That person is referred to here as the Initiator. Usually, the initiator will be a manager, a supervisor or an engineer. However, the Management of Change system should be open to all; anyone should feel free to propose changes that they believe will make the facility safer, cleaner and more profitable.The ultimate success of the Management of Change system depends on people being willing to suggest changes. There is little value in having a high quality change review process if it is never used or if it routinely bypassed. Section B - First ReviewFollowing the initiation of the Management of Change process, the next step is to carry out the First Review, which should be informal and relatively unstructured. It is sometimes referred to as the "red-face" test.Section C - Detailed EvaluationUp to this point, the change process has involved only a few people, and has been relatively informal. If the proposed change still seems to have merit it can now be submitted to the Management of Change system, where it will be evaluated by a team of people representing different disciplines and specialties. This is the detailed evaluation step.Section D - Selection and ApprovalOnce the proposed change has been thoroughly evaluated, and a list of possible recommendations prepared, facility management must select what is considered to be the best choice, and formally approve that choice.Before a change can be implemented, it must be formally approved and accepted by the plant management. This approval is necessary to meet the requirements of the process safety regulations. The approval also serves as a formal record should there ever be an accident in which the implicated as a possible cause. In practice, if the detailed evaluation in Section C was carried out thoroughly this formal acceptance step should not take long, and should be little more than a formality. Section E - New Limits / Process Safety UpdateOnce the change has been approved, new safe operating limits are defined and the engineering documentation can be updated. All persons that are affected by the new values must be informed. They must also be trained in what to do if the new limits are exceeded.Section F - NotificationBefore the change is actually implemented, all affected parties should be notified. This is usually done via e-mail. The notification process is distinct from training; it concerns those people who have some peripheral involvement with the consequences of the change, but who are not directly affected by it.Section G - ImplementationFinally, the change can be implemented.Section H - Follow-UpOnce the change has been implemented, there should be a follow-up to make sure that all precautions and preparations were handled properly. | ||||||||||||
Copyright © Sutton Technical Books 2007-2012. All rights reserved PO Box 2217 |